Construction progress report for December 2008
20.01.2009

In the period December 01-31, 2008 at the construction site of Residential complex “Berezki” in Vyshgorod town works of monolithic frame construction, interior separation wall blockwork and electrical mounting works in residential building №1 were performed.
Mounting of pillars, pylons, diaphragms and floor slabs on Floor 14 was completed with
To ensure compliance with the concrete works procedure at low outside air temperatures, concrete electric heating units were mounted and put into operation.
Within the electrical engineering section of the project,
Monolithic works in the building in general have been completed approximately at the level of 90%.